NEWS | Jan. 7, 2008

ELC Phase One Nears Completion

By Army Spc. Shanita Simmons JTF Guantanamo Public Affairs

GUANTANAMO BAY, Cuba. - The first phase of a $10.2 million project to construct the Expeditionary Legal Complex here inches closer to completion as Air Guard civil engineers put their finishing touches on its various structures.

With a scheduled phase one completion date of Jan. 15, Air Force Lt. Col. James Starnes, commander of the 474th Expeditionary Civil Engineering Squadron, said his Troopers will need to complete their part of the project so that government contractors can be brought in to paint, install communications equipment and eventually add furniture. As the 474th's tour comes to an end in February, Starnes said their replacement unit will begin its mission of maintaining the complex's various facilities to ensure they are properly functional.

When the 474th arrived here, Aug. 5, it was immediately tasked with erecting a tent city that would become living quarters for the 474th Airmen. During their six-month deployment, Starnes said his Troopers converted an abandoned airfield and a derelict cement foundation into a sprawling campus that includes all the amenities needed to facilitate military commissions. "We went from showing up here where the runway had waist-high grass to installing a tent city, to cleaning off the concrete, and then to erecting the complex. We started with a bare patch of land and had to construct various structures on it," said Starnes.

Once construction is completed in early Spring, the legal complex will include a number of buildings that will accommodate a courtroom as well as facilities that other essential parties can utilize during military commissions prceedings. The Expeditionary Legal Complex will also have cell blocks where detainees will be held during their hearings or trials, and a connecting, highly-secure walkway through which they will be escorted into the courtroom.

This mission is a unique one for the six Air National Guard units that combined to form a "mega"' group of civil engineers tasked with constructing the complex from start to finish. This particular mission became quite an adventure for these Troopers whose skill sets range from carpentry and plumbing to heavy equipment operators and mechanics when they arrived here with a blueprint created by a "Red Horse" civil engineering design group in hand and an abandoned airfield to work with.

"This particular type of construction was especially rare for this unit since our mission typically involves supporting other units by maintaining structures that have already been built," said Starnes.

Starnes credits the teamwork and effort displayed by his Troopers for enabling the construction mission to run smoothly. However, one uncontrollable challenge the 474th often faced was obtaining needed supplies that were not available on the island.

"The most difficult part of the mission was to construct a complex that is located on an island since almost everything had to be brought in from the states either on the barge or by plane," said Starnes. "There were times when we had to figure out a way of getting things here either by borrowing it from someone on the island or just waiting on the stuff to get here from a supplier in the States.

"Once the ceilings and floors are installed within the complexes various structures, the 474th will have completed the final step in their phase of the overall project. Despite the challenges, Starnes said he is proud of his Troopers for being able to come aboard and efficiently complete their mission by the specific target date. Starnes expressed his gratitude for the highly-skilled Troopers assigned to the Indiana Air National Guard's 122nd, the Wisconsin Air National Guard's 128th, the Vermont Air National Guard's 158th, the Ohio Air National Guard's 121st and the California Air National Guard's 163rd Prime Base Engineer Emergency Forces who stepped up to perform this mission.

"We are extremely proud of what we have accomplished. I am proud of the Troopers who left their civilian jobs and families in order to come down here and build this complex," said Starnes. "Even though this is a very essential mission that helps fight the War on Terror, the Troopers came down here to do something that they enjoy doing and that they are trained to do."

 

 

Related Articles
Members of the 51st Civil Support Team, Michigan National Guard, U.S. Coast Guard, and other responders are on the St. Marys River during the culminating training event for Operation Iron Wave at the Soo Locks in Sault Ste. Marie, Michigan. Operation Iron Wave is an interagency training exercise that prepares local, state and federal agencies to respond to threats against critical infrastructure. Photo by Capt. Cameron McPhail.
Michigan Guard Strengthens Emergency Response Partnerships
By Capt. Cameron McPhail, | Aug. 5, 2026
SAULT STE. MARIE, Mich. – Military personnel including the Michigan National Guard, first responders and government agencies from across the nation came together July 27-31 during Operation Iron Wave, a multi-day joint...

Air Force Brig. Gen. Phillip L. Mallory, Hawaii Air National Guard commander, passes the Headquarters Hawaii Air National Guard Recruiting and Retention Flight guidon to Air Force Lt. Col. Michael Buendia, Headquarters Hawaii Air National Guard Recruiting Flight commander, symbolizing Buendia's acceptance of command of the flight during the unit's activation ceremony held at Pearl Highlands Center in Pearl City, Hawaii, Aug. 1, 2026. Before the flight’s activation, recruiting and retention efforts fell under the Hawaii Air National Guard personnel directorate. The establishment of the Hawaii Air National Guard’s first dedicated Recruiting and Retention Flight creates a team focused on recruiting new Airmen, retaining experienced personnel and strengthening accession support across the organization. Photo by Tech. Sgt. Orlando Corpuz.
Hawaii Air Guard Establishes Recruiting and Retention Flight
By Tech. Sgt. Orlando Corpuz, | Aug. 5, 2026
PEARL CITY, Hawaii – The Hawaii Air National Guard activated its first Recruiting and Retention Flight during a ceremony Aug. 1 at the Hawaii Air National Guard recruiting offices in Pearl Highlands Center, establishing a...

A U.S. Air Force special tactics Airman from the Kentucky Air National Guard’s 123rd Airlift Wing jumps into Henry E. Rohlsen Airport near Christiansted in St. Croix, U.S. Virgin Islands, Aug. 26, 2025 as part of Emerald Warrior 25.2, a large-scale special operations exercise being staged in multiple locations by Air Force Special Operations Command. The Airman, joined by 10 other combat controllers and pararescuemen, took control of the airfield to receive follow-on aircraft in support of simulated combat and contingency operations. Photo by Phil Speck.
Air National Guard Details Bonuses, Policy Changes Amid ‘Summer Surge Incentives’
By Master Sgt. Erich Smith, | Aug. 4, 2026
ARLINGTON, Va. – The Air National Guard is rolling out sweeping recruiting and retention transformation initiatives – removing accession barriers, expanding enterprise support and reshaping how it competes for the talent...